Well - we gott'r done. The wine room is finished and we are
too!!!!!!!! So now on to the reason for all this. Wade wanted to see
the final so here it is.
We had a 2x4 area that was insulated and paneled. First of
all we added a 1 1/2" foam sheet over the paneling. Then we
framed a 2x6 interior wall over that and stuffed with 6" of R19
insulation. We then sheeted with 1/2" OSB and primered and
painted it. Our walls are now approx 11 1/2" thick and they are
about R35. Sheeted the ceiling and added R30 insulation.
Added a 6500 Goldstar A/C in wall and hung a 2" solid metal sheeted
prehung door. Final size is approx 7' x 11'. Had some
cabinets that were removed from an old office and found a use for
them. Sure would like a deep sink but will have to be outside
somewhere. Let's see if I can figure out how to load some
pictures for ya'll.
what we started with
adding foamboard over paneled insulated wall
2x6 framed wall with R19 insulation, osb and a/c.
foamboard and 2x6 walls
walls painted and shows work area
end opposite work area
Have a bunch of commercial wine so filled some of the shelves with
these. I also started a Wine Selection Gewurztraminer today and
am waiting on a cab from George. Gonna be fun!!! Also, a
friend of mine gave me a couple of 6 gallon carboys today so we are in
good shape.
Hope all of this is okay and am looking forward to lots of fun form chats. Half of the fun was the road getting there!!!
rrawhide
central california